Solve discounted, infinite horizon MDPs via linear programming.

Usage

solve_MDP_LP(
  model,
  method = "LP",
  horizon = NULL,
  discount = NULL,
  inf = 1000,
  lpSolve_args = list(),
  ...,
  matrix = NULL,
  continue = FALSE,
  verbose = FALSE,
  progress = NULL
)

Arguments

model

an MDP problem specification.

method

string; one of the following solution methods: 'LP'

horizon

Only infinite-horizon MDPs with horizon = Inf are supported.

discount

only undiscounted MDPs with discount = 1 are supported.

inf

value used for infinity when calling lpSolve::lp(). This should me much larger than the largest absolute reward in the model.

lpSolve_args

a list with additional arguments passed on to lpSolve::lp().

...

further parameters are passed on to the solver function.

matrix

logical; if TRUE then matrices for the transition model and the reward function are taken from the model first. This can be slow if functions need to be converted or do not fit into memory if the models are large. If these components are already matrices, then this is very fast. For FALSE, the transition probabilities and the reward is extracted when needed. This is slower, but removes the time and memory requirements needed to calculate the matrices.

continue

logical; show a progress bar with estimated time for completion.

verbose

logical or a numeric verbose level; if set to TRUE or 1, the function displays the used algorithm parameters and progress information. Levels >1 provide more detailed solver output in the R console.

progress

not supported by this solver.

Value

solve_MDP() returns an object of class MDP or MDPSample which is a list with the model specifications (model), the solution (solution). The solution is a list with the elements that depend on the used method. Common elements are:

  • method with the name of the used method

  • parameters used.

  • converged did the algorithm converge (NA) for finite-horizon problems.

  • policy a list representing the policy graph. The list only has one element for converged solutions.

Details

A linear programming formulation was developed by Manne (1960) and further described by Puterman (1996). For the optimal value function, the Bellman equation holds:

$$ v^*(s) = \max_{a \in \mathcal{A}}\sum_{s' \in \mathcal{S}} p(s, a, s') [ r(s, a, s') + \gamma v^*(s')]\; \forall a\in \mathcal{A}, s \in \mathcal{S} $$

The maximization problem can reformulate as a minimization with a linear constraint for each state action pair. The optimal value function can be found by solving the following linear program: $$\text{min} \sum_{s\in S} v(s)$$ subject to $$v(s) \ge \sum_{s' \in \mathcal{S}} p(s, a, s')[r(s, a, s') + \gamma v(s')],\; \forall a\in \mathcal{A}, s \in \mathcal{S} $$

Note:

  • The discounting factor has to be strictly less than 1.

  • The used solver does not support infinity and a sufficiently large value needs to be used instead (see parameter inf).

  • Additional parameters to to solve_MDP are passed on to lpSolve::lp().

References

Manne, Alan. 1960. "On the Job-Shop Scheduling Problem." Operations Research 8 (2): 219-23. doi:10.1287/opre.8.2.219 .

Puterman, Martin L. 1996. Markov decision processes: discrete stochastic dynamic programming. John Wiley & Sons.

Examples

data(Maze)

# we change the discount to 0.9 since LP is only implemented for discounted MDPs.  
maze_solved <- solve_MDP(Maze, discount = 0.9, method = "LP:LP", verbose = TRUE)
#> creating 44 constraints ... took 0.001 seconds.
#> running LP solver ... took 0.001 seconds.
maze_solved
#> MDPModel, MDP - Stuart Russell's 3x4 Maze
#>   Discount factor: 0.9
#>   Horizon: Inf epochs
#>   Size: 4 actions / 11 states
#>   Storage: transition prob as matrix / reward as matrix. Total size: 47.3 Kb
#>   Start: s(3,1)
#>   Model list components: ‘name’, ‘discount’, ‘horizon’, ‘states’,
#>     ‘actions’, ‘start’, ‘transition_model’, ‘reward’, ‘info’,
#>     ‘absorbing_states’, ‘solution’
#> 
#>   Solved:
#>     Method: ‘lp’
#>     Solution converged: TRUE
#>   Solution list components: ‘method’, ‘policy’, ‘converged’,
#>     ‘solver_out’
policy(maze_solved)
#>     state         V action
#> 1  s(1,1) 0.5810788  right
#> 2  s(2,1) 0.4614351     up
#> 3  s(3,1) 0.3508265     up
#> 4  s(1,2) 0.7322953  right
#> 5  s(3,2) 0.3002100  right
#> 6  s(1,3) 0.8895585  right
#> 7  s(2,3) 0.5499803     up
#> 8  s(3,3) 0.3974613     up
#> 9  s(1,4) 0.0000000   left
#> 10 s(2,4) 0.0000000     up
#> 11 s(3,4) 0.1606287   left